Clean Water Shreveport

Year Eight Annual Report

What's been completed?

0 feet

Pipe Line Inspected

0

Lift Stations Assessed

0

Manhole Inspections

0 feet

Pipe Line Cleaned

Progress Overview

No Pipes Cleaned

All Pipes Cleaned

The Gravity Sewer Preventative Maintenance Program includes routine cleaning and cleaning required per the Consent Decree SSA activities. According to Consent Decree requirements, the City is responsible for cleaning greater than 15 percent of the City’s WCTS annually and 100 percent of the system no later than 84 months following the Effective Date of the Consent Decree. The City has attempted to clean 100% of the pipes, rather than just the 15-inch diameter and greater as part of the SSA investigations.

Start

Phase 1 Projects

Phase 2 Projects

Phase 3 Projects

Finish

The City constructed 30 total projects within SSA Phase 1. All 30 projects have reached final completion. Table 3-5 in the Year 8 Annual Report below provides a summary of the project status of each of the Phase 1 RMP Projects. During Consent Decree Year 7, the City advanced one (1) project to final completion, “175.177.178.179 – Jewella & Greenwood” on June 12, 2020.

A total of 17 total construction projects were developed based on the Phase 2 RMP. All 17 projects have reached final completion. One (1) project (2-SH1) reached functional completion and 11 projects reached final completion during the Year 7 reporting period. Table 3-6  in the Year 8 Annual Report  below provides a summary of the actual completion dates for each of the Phase 2 RMP Projects.

A total of 14 total projects were developed based on the Phase 3 RMP. During Year 8 each of these projects has advanced into detailed design.  Bidding and construction of Phase 3 projects were placed on hold during Consent Decree Year 6 due and continued to hold through Year 8.

Start of Critical Projects

Finish of Critical Projects

In early 2020 (Year 6), 19 projects were selected to mitigate SSOs, address regulatory compliance, and maintain reliable utility service within the City’s wastewater and water utilities. The City continued to advance the delivery of these projects through the Consent Decree Year 8 reporting period.

To see a detailed list of Critical Projects click here and navigate to page 28.

Sanitary Sewer Overflow Occurrences

Sanitary Sewer Overflows, SSOs, can be caused by a multitude of things. The most common occurrences are caused by an inflow of excessive stormwater into sewer lines, malfunctioning lift stations, broken sewer lines, and more.

Q&As on COVID-19 and related health topics

Nunc at tempor odio, nec fringilla risus. Curabitur gravida urna vitae lacus volutpat tristique. Suspendisse porttitor enim nec lorem venenatis viverra. Nullam cursus tortor vel lorem consectetur dictum

What are the most common side effects after getting the vaccine?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien

When will vaccine be available to me?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien

Can I choose wich vaccine I get?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien

When will vaccine be available to me?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien

Do I still need to wear a mask and socially distance after getting the vaccine?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien

Should I take chloroquine phosphate used to treat disease in aquarium fish to prevent or treat COVID-19?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien

Do the vaccines work against the emerging variants of SARS-CoV-2?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien

What do we know about the vaccines’ long-term safety?

Maecenas blandit scelerisque dolor, non accumsan tortor finibus sit amet. Suspendisse fringilla nulla ante, eget porttitor ex laoreet et. Vestibulum lobortis, purus nec varius pellentesque, nunc augue consectetur neque, id euismod augue ipsum et ante. Aenean vel tortor eget mauris tempus tincidunt a egestas sapien