Clean Water Shreveport

Phase 1

Overview

The City constructed 30 total projects within SSA Phase 1. All 30 projects have reached final completion. The City Began construction in various areas in 2016 working within nine neighborhoods including Allendale, Cedar Grove, and Hollywood Heights.

Detailed Project Information

ProjectProject TypeContractorBudgetStatus
Installation of Inflow PreventorsWastewaterYor-Wic$325,000 Completed
Cedar Grove & Slack Lift StationWastewaterDixie Overland$288,000 Completed
Meadow Parkway Lift Station RehabWastewaterDixie Overland$207,000 Completed
CIPPL Package 4WastewaterInsituForm$11,633,000 Completed
CIPPL Package 3WastewaterSAK$7,902,000 Completed
CIPPL Package 2WastewaterSuncoast$13,637,000 Completed
CIPPL Package 1WastewaterMitchell Contracting$9,145,000 Completed
Jewella & GreenwoodWastewaterPM Rehab$3,316,000 Completed
Mansfield Rd & CorbittWastewaterS&J$5,537,000 Completed
Hearne & Hollywood TrunkmainWastewaterHemphill$11,953,000 Completed
Jewella & ClarkeWastewaterPulley$5,134,000 Completed
Henry & KennedyWastewaterPM Rehab$5,576,000 Completed
Hollywood & SingletaryWastewaterBelt Construction$4,624,000 Completed
Greenwood & Junior PlaceWastewaterWicker Construction$1,541,000 Completed
Monkhouse & InterstateWastewaterWicker Construction$1,207,000 Completed
Standard OilWastewaterWicker Construction$1,316,000 Completed
Linwood & LineWastewaterPM Rehab$4,460,000 Completed
Linwood & FairfieldWastewaterJohn Plott$13,208,000 Completed
Hollywood & KennedyWastewaterWicker Construction$13,288,000 Completed
Wyngate & WallaceWastewaterSuncoast$10,984,000 Completed
Joe Louis & EversWastewaterDon Barron$3,181,000 Completed
Sunset Acres & Cargill (Hickory Ridge LS)WastewaterHemphill$13,098,000 Completed
Karen & DollarwayWastewaterWicker Construction$1,814,000 Completed
Garden ValleyWastewaterWicker Construction$3,147,000 Completed
W Canal & Valleyview TrunkWastewaterJohn Plott$8,274, 000Completed
Hollywood Ditch/W 70thWastewaterDon Barron$4,300,000 Completed
Cedar Grove Trunk MainWastewaterYor-Wic$7,111,000 Completed
Union & WallaceWastewaterJohn Plott$6,356,000 Completed
Garden Valley Unit 2WastewaterJohn Plott$3,551,000 Completed
Wyngate & W 84thWastewaterS&J$5,593,000 Completed
Dowdell & FairfieldWastewaterWicker Construction$8,868,000 Completed