Clean Water Shreveport

Critical Projects

Overview

The City completed an extensive capital improvement planning effort to identify additional Critical Projects for delivery and execution in the coming years. These projects were selected by applying an Integrated Planning Approach to consider all compliance and utility obligations. As a result, this group of projects provides a balanced investment into both the City’s wastewater and water utilities. The projects were identified to address three main goals: 1) address and mitigate sanitary sewer overflows 2) support the City’s regulatory compliance obligations – wastewater and water, and 3) enable reliable utility service to continue. While these projects vary in their level of definition, the current cost for completing design and construction activities is estimated to be approximately $415 million. It is expected that additional activities, initiatives, and projects will be identified in future years as the City continues to progress ongoing planning activities.

A summary of the City’s Critical Projects is presented below.

The City has made significant progress in delivering its Critical Project Portfolio. Current projects under construction were identified in early 2020 to support the City’s obligation to provide reliable utility service to its customers and address known facility and operational issues being experienced by the utility. The development and delivery of each project is managed through a defined Stage / Gate process that provides an opportunity for the City’s Water and Sewerage Department and utility staff involvement at key milestones.

Learn more about the Critical Projects below.

A summary of the City’s Critical Projects is presented below.

Shreveport, Louisiana, USA
  • Wastewater Projects

  • Critical Wastewater Projects

    Information can be found in the City Council Update Presentation.
    ProjectProject TypeDesignerBudgetStatus
    Wallace Interceptor at Boggy BayouWastewaterAillet, Fenner, Jolly, & McClelland, Inc.$3,000,000Future
    North Pierre Lift Station Roof RepairWastewaterKSA Engineers$73,700Completed
    Stoner Lift Station Emergency RepairWastewaterBalar and Associates$1,475,000Completed
    North Regional WWTP- Levee Repair #2WastewaterCoyle Engineering$200,000In-Progress
    Southern Trace Lift Station ImprovementsWastewaterBurk-Kleinpeter, Inc.$300,000Completed
    North Regional WWTP- Levee Repair #1WastewaterCoyle Engineering$157,192Completed
    City Wide Water & Sewer On Demand RepairWastewaterCity of Shreveport$3,000,000In-Progress
    Lucas & North Regional WWTP UVWastewaterBalar Associates, Inc$13,500,000Future
    Public Landing Lift Station ImprovementsWastewaterRaley and Associates$700,000Completed
    Stratmore Lift Station RehabilitationWastewaterHalf & Associates$650,000Future
    Lift Station RehabilitationsWastewaterBurk-Kleinpeter, Inc.$4,577,000In-Progress
    “Sludge Farm” Facility ImprovementsWastewaterKSA Engineers$2,500,000In-Progress
    Golf Link Drive SewerWastewaterCity of Shreveport$312,000Completed
    719 Edwards Sewer Main RehabilitationWastewaterCity of Shreveport$650,000Completed
    Exposed Sewer Main in Bayou PierreWastewaterKSA Engineers$750,000Future
    McNeil Slope Stability ImprovementsWastewaterRaley & Associates, Inc.$650,000On-Hold
    Manhole Rehabilitation & I/I ReductionWastewaterTBD$1,557,861In-Progress
    Caddo Bossier Port-Sewer RepairWastewaterNA$78,000Completed
    Southern Force Main ImprovementsWastewaterTBATBAFuture
    Cedar Force Main ImprovementsWastewaterTBATBAFuture
    Stoner Force Main ImprovementsWastewaterTBATBAFuture
    Wallace Force Main ImprovementsWastewaterTBATBAFuture
    Gravity Sewer Main Improvements packageWastewaterTBATBAFuture
    Lift Station Rehabilitation PackageWastewaterTBATBAFuture
    Brookmeade & Querbes SSO MitigationWastewaterTBATBAFuture
    Dilg League SSO MitigationWastewaterTBATBAFuture
    Water Main Renewal and Replacement ProgramWastewaterTBATBAFuture
  • Water Projects

  • Critical Water Projects

    Information can be found in the City Council Update Presentation.
    ProjectProject TypeDesignerBudgetStatus
    Amiss Ozone Water Treatment PlantWaterBurns and McDonnell$36,500,000In-Progress
    Fire Protection/Flow Rating and Property Insurance
    Association of Louisiana (PIAL) Requirements
    WaterTBATBAFuture
    Revised Lead and Copper Rule ObligationsWaterTBATBAFuture
    Cross Lake and Dam Spillway RehabilitationWaterTBATBAFuture
    Amiss Water Treatment Plant
    Transmission Piping and Valve Replacement
    WaterTBATBAFuture
    Water Pump Station Stand by Generator installationWaterTBATBAFuture
    Review & Update Water System Risk
    Resiliency Assessment and Emergency Response Plan
    WaterTBATBAFuture
    Twelve Mile Bayou Pump Station Discharge Main Evaluation and TestingWaterTBATBAFuture
    Citywide Smart Water Meter ReplacementWaterTBATBAFuture
    70th & Pines Boster Pump Station RehabilitationWaterTBATBAFuture
    St. Vincent Elevated Storage Tank RehabilitationWaterTBATBAFuture
    West Shreveport Elevated Storage Tank RehabilitationWaterTBATBAFuture
    Water System Winterization and Resiliency ImprovementsWaterTBATBAFuture
    Water Main Renewal and Replacement ProgramWaterTBATBAFuture
    Water SCADA Master Plan and ImplementationWaterTBATBAFuture

Critical Wastewater Projects

Information can be found in the City Council Update Presentation.
ProjectProject TypeDesignerBudgetStatus
Wallace Interceptor at Boggy BayouWastewaterAillet, Fenner, Jolly, & McClelland, Inc.$3,000,000Future
North Pierre Lift Station Roof RepairWastewaterKSA Engineers$73,700Completed
Stoner Lift Station Emergency RepairWastewaterBalar and Associates$1,475,000Completed
North Regional WWTP- Levee Repair #2WastewaterCoyle Engineering$200,000In-Progress
Southern Trace Lift Station ImprovementsWastewaterBurk-Kleinpeter, Inc.$300,000Completed
North Regional WWTP- Levee Repair #1WastewaterCoyle Engineering$157,192Completed
City Wide Water & Sewer On Demand RepairWastewaterCity of Shreveport$3,000,000In-Progress
Lucas & North Regional WWTP UVWastewaterBalar Associates, Inc$13,500,000Future
Public Landing Lift Station ImprovementsWastewaterRaley and Associates$700,000Completed
Stratmore Lift Station RehabilitationWastewaterHalf & Associates$650,000Future
Lift Station RehabilitationsWastewaterBurk-Kleinpeter, Inc.$4,577,000In-Progress
“Sludge Farm” Facility ImprovementsWastewaterKSA Engineers$2,500,000In-Progress
Golf Link Drive SewerWastewaterCity of Shreveport$312,000Completed
719 Edwards Sewer Main RehabilitationWastewaterCity of Shreveport$650,000Completed
Exposed Sewer Main in Bayou PierreWastewaterKSA Engineers$750,000Future
McNeil Slope Stability ImprovementsWastewaterRaley & Associates, Inc.$650,000On-Hold
Manhole Rehabilitation & I/I ReductionWastewaterTBD$1,557,861In-Progress
Caddo Bossier Port-Sewer RepairWastewaterNA$78,000Completed
Southern Force Main ImprovementsWastewaterTBATBAFuture
Cedar Force Main ImprovementsWastewaterTBATBAFuture
Stoner Force Main ImprovementsWastewaterTBATBAFuture
Wallace Force Main ImprovementsWastewaterTBATBAFuture
Gravity Sewer Main Improvements packageWastewaterTBATBAFuture
Lift Station Rehabilitation PackageWastewaterTBATBAFuture
Brookmeade & Querbes SSO MitigationWastewaterTBATBAFuture
Dilg League SSO MitigationWastewaterTBATBAFuture
Water Main Renewal and Replacement ProgramWastewaterTBATBAFuture

Critical Water Projects

Information can be found in the City Council Update Presentation.
ProjectProject TypeDesignerBudgetStatus
Amiss Ozone Water Treatment PlantWaterBurns and McDonnell$36,500,000In-Progress
Fire Protection/Flow Rating and Property Insurance
Association of Louisiana (PIAL) Requirements
WaterTBATBAFuture
Revised Lead and Copper Rule ObligationsWaterTBATBAFuture
Cross Lake and Dam Spillway RehabilitationWaterTBATBAFuture
Amiss Water Treatment Plant
Transmission Piping and Valve Replacement
WaterTBATBAFuture
Water Pump Station Stand by Generator installationWaterTBATBAFuture
Review & Update Water System Risk
Resiliency Assessment and Emergency Response Plan
WaterTBATBAFuture
Twelve Mile Bayou Pump Station Discharge Main Evaluation and TestingWaterTBATBAFuture
Citywide Smart Water Meter ReplacementWaterTBATBAFuture
70th & Pines Boster Pump Station RehabilitationWaterTBATBAFuture
St. Vincent Elevated Storage Tank RehabilitationWaterTBATBAFuture
West Shreveport Elevated Storage Tank RehabilitationWaterTBATBAFuture
Water System Winterization and Resiliency ImprovementsWaterTBATBAFuture
Water Main Renewal and Replacement ProgramWaterTBATBAFuture
Water SCADA Master Plan and ImplementationWaterTBATBAFuture

View Current Completed Projects

Additional Resources

FAQs

Clean Water Shreveport The City of Shreveport’s Department of Water...

Read More